After Log Splitter, is installed, it should be checked before starting. This is the first and important step of preparing for its operation. Let’s take a look!
- Check whether the fly knife and the bottom knife are tight according to the specified tightening torque.
- The gap between the flying knife and the bottom knife of the integrated crusher should be within the range of 0.5-1mm (check with thickness inspection).
- There should be no metal debris in the machine.
- Rotate the pulley of the comprehensive crusher by hand for more than one week without collision.
- The tension of the V-belt is moderate, and the belt cover should be installed.
- The electrical system is in a normal state.
- The joints of the hydraulic system are well sealed and there is no oil leakage.
- The direction of rotation of the knife roller and the feeding roller is correct.
In addition, the dry run of the Performance Built Log Splitter is 1-4 hours. After the dry run is normal, load cutting can be carried out.